News
» Go to news mainCampus Construction Update
AC CAMPUS CONSTRUCTION UPDATES
Week of Aug 21st Ìý– Sept 2nd ÌýÌý
The Campus Construction Update is a regular feature of the Weekly E-Bulletin in an effort to keep the campus community informed of any potential distruptions to regular work practices during summer construction.
Campus Interior of Buildings
Week of August 21st Ìý
Piping installation to continue in EXT. ENG., NEW COX, POUTRY, OLD COX, AQUACULTURE and MACRAE Buildings. (Chance of minor noise with this work)
For the work in NEW COX it will be through a part of the hallway and through some computer, physics labs. Some items in this area will have to be move for work to proceed and will be coordinated with DAL.Ìý (Expect some disruption with some of this work).
For the work in MACRAE it will be through a part of the hallway and through staff areas. Some items in this area will have to be move for work to proceed and will be coordinated with DAL. (Expect some disruption with some of this work).
One small piping crew to start back working in BOULDEN, CHUTE, HALEY, JENKINS, RUMINANT, and HANCOCK, DAIRY, CUMMINGS. (Chance of minor noise with this work)
Piping crew to Hydro test MACRAE.
Demolition to continue in OLD COX, EXT. ENG Buildings (Chance of minor noise with this work)
Civil work for concrete pads will follow in POULTRY, EXT. ENG., OLD COX, NEW COX Buildings (Chance of minor noise with this work)
Electrical and Control work to continue throughout buildings for equipment mounting and conduit runs. CHUTE, BOULDING, RUMINANT, LANGILLE, HALEY, JENKINS HALL, HANCOCK, EXT. ENG., AQUA, CUMMINGS, BANTING, and MACRAE Buildings. (Chance of minor noise with this work, hammer drilling, etc.)
Week of August 28th
Piping installation to continue in EXT. ENG., NEW COX, POUTRY, OLD COX, AQUACULTURE and MACRAE Buildings. (Chance of minor noise with this work)
For the work in NEW COX it will be through a part of the hallway and through some computer, physics labs. Some items in this area will have to be move for work to proceed and will be coordinated with DAL.Ìý (Expect some disruption with some of this work).
For the work in MACRAE it will be through a part of the hallway and through staff areas. Some items in this area will have to be move for work to proceed and will be coordinated with DAL. (Expect some disruption with some of this work).
One small piping crew to start back working in BOULDEN, CHUTE, HALEY, JENKINS, RUMINANT, and HANCOCK, DAIRY, CUMMINGS. (Chance of minor noise with this work)
Piping crew to Hydro test MACRAE.
Demolition to continue in OLD COX, EXT. ENG Buildings (Chance of minor noise with this work)
Civil work for concrete pads will follow in POULTRY, EXT. ENG., OLD COX, NEW COX Buildings (Chance of minor noise with this work)
Electrical and Control work to continue throughout buildings for equipment mounting and conduit runs. CHUTE, BOULDING, RUMINANT, LANGILLE, HALEY, JENKINS HALL, HANCOCK, EXT. ENG., AQUA, CUMMINGS, BANTING, and MACRAE Buildings. (Chance of minor noise with this work, hammer drilling, etc.)
Campus Exterior South
Testing Heating System
Pipe Cumming to Jenkins
Clean & flush lines
Pour Concrete in Bollards.
Landscape areas disturbed.
Install covers on exposed pipes
North
Continue road work on old Cox Road
Backfilling Pipe at Banting & Old Cox
Install Pipe at Old Cox
Continue work in Manholes
Continue Propane Pad at Old Cox
Testing Lines
Start work in Tunnel
Flush & Clean lines
Reinstate curbs & landscaping & patch asphalt.
COX BUILDING
Complete minor caulking deficiencies on interior/exterior (This Thursday)
Minimal repointing between greenhouses
Repointing panel in section B
Wash down section A, B and C
Dismantle Scaffold and hoarding
Demobilize and clean-up site
NEW - CUMMING HALL
Roof replacement begins Monday August 21st.
Any questions or concerns please contact:
Stephanie MacKenzie
Project Manager Facilities Management
902.956.4492
Stephanie.Mackenzie@dal.ca
Recent News
- Holiday Hours
- From Academia to Agriculture: Former PhD student and supervisor launch innovative vertical farming venture
- Community Representative ‑ Animal Care and Use
- New Face on Campus
- Sowing Seeds of Knowledge: A Gardener’s Journey with DeAnne Pelchat
- ºÚÁϳԹÏÍøAdvising Summit
- Legacy Awards 2024
- Regenerative Agrourbanism